When this applies
when evaluating any organization's contracting/compensation structure, check whether cost is reimbursed (cost-plus) or fixed, since that structure predicts whether the org will optimize for speed/efficiency or for headcount/billable effort
The takeaway
Compensation/contract structure that rewards cost incurred rather than outcome delivered will structurally produce slowness and cost bloat, regardless of individual intentions.
Why it works
Under cost-plus, revenue scales with cost incurred, so adding people or time increases payout without penalty, eliminating the natural pressure to go faster or cheaper.
One level up
Incentive structure, not culture or talent, is usually the root cause of an organization's speed or stagnation.
Where it stops holding
This stops working for genuinely novel, high-uncertainty projects where no one can estimate true cost upfront — there cost-plus may be the only way to get suppliers to participate at all.
Detail
rule: Cost-plus structures are suited to wartime/urgent/uncertain-cost projects, not to mature, equilibrium industries, where they instead cause stagnation.
threshold: Signal: more people added to a project without the project visibly moving faster.
rationale: Without strong downward pressure on cost, incentives are not aligned with moving fast and lean, and this pattern recurs across cost-plus industries (aerospace primes, nuclear utilities, space launch before SpaceX).
In their words
Once you get to equilibrium I don't think that structure makes sense at least not to motivate the right behaviors.